top of page
Wasdell HVAC

Wasdell

HVAC modification

Production Line 7 at Wasdell, Swindon was operating at a <30% relative humidity. Bassaire were tasked with reducing the RH in the room to <20%.    

​

Basasire successfully reduced the relative humidity by rerouting the return ductwork so that it bypassed the air handling unit and connected back in before the dehumidifier. Due to the returning air no longer passing through the filters in the AHU, an F9 filter was also installed in the supply duct.


This project was successfully completed within just 10 days due to a strict deadline set by the client.

bottom of page